FY22 Facilities Task Order B – Refurbishment and Infrastructure Projects focused on Facility Improvements within the NCI at Frederick Campus
2022 财年设施任务订单 B — 翻新和基础设施项目,重点关注弗雷德里克校区 NCI 内的设施改进
基本信息
- 批准号:10716465
- 负责人:
- 金额:$ 612.82万
- 依托单位:
- 依托单位国家:美国
- 项目类别:
- 财政年份:2022
- 资助国家:美国
- 起止时间:2022-04-26 至 2025-10-24
- 项目状态:未结题
- 来源:
- 关键词:AccelerationAccreditationAgreementAmericanAreaAwardBudgetsBusinessesCertificationCodeComputer softwareContingency FundContractorContractsCost ControlCritical PathwaysDataDevelopmentDocumentationEffectivenessElementsEngineeringEnsureEventExhibitsExpenditureFeedbackFundingGovernmentGrowthGuidelinesHourInfrastructureMaintenanceManualsMethodologyMonitorNotificationParentsPerformancePoliciesProceduresProcessProfessional OrganizationsQuality ControlReaction TimeRecoveryRegulationReportingScheduleServicesSiteSpecific qualifier valueStrategic PlanningSystemTechniquesTimeUnited States National Institutes of HealthWorkauthoritycostcost estimatedesignimprovedindexingmeetingsoperationprofessional atmosphereprogramsquality assurancerisk mitigation
项目摘要
Statement of Work Appendix: General Requirements FY22 Facilities Task Order B – Refurbishment and Infrastructure Projects focused on Facility Improvements within the NCI at Frederick Campus1. General RequirementsIn accordance with FFRDC SOW, Maintenance plans shall be compatible with elements of the current Interagency Agreement including any revisions thereto, between the U.S. Army Garrison (USAG), Fort Detrick, and the NCI at Frederick with the Contractor performing those functions designated as the responsibility of the NCI at Frederick. The Contractor’s work and responsibility shall include all planning, programming, engineering, maintenance, administration, and management necessary to provide work as specified. The Contractor shall ensure that staffing hours and levels are sufficient to meet the Government’s needs. The work shall be conducted in accordance with the FFRDC SOW, Exhibit 1, Regulations/Certifications/Accreditations/Guidelines. 2. Facility Operations & Management of Planned WorkThe Contractor shall work closely with the Government to determine needs and priorities associated with customer requirements. The Contractor shall coordinate with EHS during project concept, design, and closeout to ensure project milestones submitted in project schedules are reflective of both FME and EHS requirements. a) Planned Work ManagementThe Contractor shall have the authority to manage all aspects of work orders to include, but not limited to, the use of approved project budget, schedule, and project quality. The Contractor shall estimate the project contingency needs using qualitative and quantitative metrics, approval must be obtained in accordance with the task order terms and conditions prior to any release of contingency funds. The Contractor shall keep the customer and FME COR informed of project progress. All project changes must follow Facility Change Management process. During task order performance when an impact to scope, cost, schedule or performance is identified the Contractor shall notify the Government by inclusion in the monthly progress notification. If the critical path is changed the notification shall include an explanation of the cumulative events that resulted in the change, Fragnet, and risk mitigation strategy including schedule recovery and/or acceleration. Contractor shall coordinate across all directorates to ensure each project has an integrated Master Schedule. b) Planned Work CloseoutThe Contractor shall work collaboratively with the FME COR to establish standard practices for project closeout. The Contractor shall consistently apply closeout practices. Contractor shall ensure project
09/26/2019
2
close-out consideration in scope/cost/schedule account for processes across all Contractor business directorates.
3.Facility Strategic Planning
As a component of the development and ongoing growth and refinement of the Facilities Operations Manual required per the parent IDIQ, the Contractor shall continually assess and analyze all aspects of Facility, Maintenance and Engineering activities. The Contractor shall seek to consider procedures to improve efficiency in facilities, maintenance, engineering, and renovation/ alteration/ maintenance/ refurbishment/ improvement projects. The Contractor shall to seek to identify improvements in all aspects of performance that will increase the effectiveness or efficiency of contract performance. Identified improvements shall align with Government requirements, customer feedback, and stakeholder input.
4.Quality Assurance/Quality Control (QA/QC)
Contractor shall develop and maintain a baseline program of quality assurance (QA) and quality control (QC) that will document performance and quality standards, and management controls and assessment techniques to ensure components, services, and products meet HHS/NIH/NCI’s design criteria and other governing and applicable specifications. The Contractor shall identify policies and procedures to improve performance and efficiencies in all project areas. The Contractor shall establish and maintain an effective quality control (QC) system. QC consist of plans, procedures, and organization necessary to produce a product which complies with the Contract requirements.
Contractor shall provide Construction Quality Management (CQM) plan to ensure that work is performed according to plans and specifications, on time, within a defined budget, and a safe work environment. Contractor shall provide a detailed Quality Control Plan (QCP) for all projects > $50,000.00, contractor shall identify certified Quality Control Manager for all projects >$1m. The contractor has primary responsibility for compliance with plans and specifications.
5.Cost control (Estimating
The Contractor shall use historical data, market analysis, and “RS Means” software to develop cost estimates of any change requests and/ or impact analysis reports. The Contractor must adhere to the requirements established in the DRM (Section 1.6.3). The Contractor shall also follow American Society of Professional Estimators (ASPE) methodology.
6.Meetings
The following meetings between the Contractor and NCI designated representatives are held, non-severable projects awarded on task orders shall be included in content and discussions as applicable:
1)FME Operations Meeting (Weekly)
This meeting to include FME, MOSB, and FME COR shall be held weekly to review and discussprogram operational priorities and performance.
2)Plan of the Week (POW) Meeting (Weekly)
09/26/2019
3
This meeting to include FME, EHS, Program Representatives, MOSB, OSO and FME and EHS CORs shall be held weekly to review status of all new work orders, work orders in development, and approved work orders.
7.Tracking and Monitoring of Metrics
Under the requirements of the NCI FFRDC Operational Task Order the Contractor and the FME COR shall identify Key Performance Indicators that have designated targets. Once identified, the Contractor shall track and monitor metrics to the identified KPIs. For planned work awarded under non-severable task orders, the Contractor shall track and monitor, at a minimum, the following metrics:
•Percentage of Work orders (WO) rescheduled from the initial approved schedule.
•Work order expenditure by type:
oGeneral Work Order
oInspection
oEmergency
oCorrective Maintenance
•Percentage of Planned WOs verses all other WOs
•Backlog (Funding threshold)
oSpecial Assists
•Work order backlog including 30+ days total and per shop
•Work order completion response time per shop
•Shop support to FME Planned Work Orders, hours and percent of total
8.Contingency
Contingency notifications shall include:
1-Narrative explanation of need for contingency use
2-Contingency log tracking each instance of contingency use, amount, subtotal, and remainingbalance
3-Contingency Index Calculation
•Contingency Index = Physical % Complete / % Contingency Expended.
4-Supporting documentation as applicable, including but not limited to:
•PCO
•RFIs
•Bulletins
•Submittals
•Change order code:
oAE error omissions
oUnforeseen site conditions
oUser directed change requests
•Inspections
•Schedule change -Fragnet
09/26/2019
4
Additional contingency requirements:
1.If LBR’s ‘Best & Final’ subcontractor award is lower than LBR subcontractor estimateper NCI award amt, then all excess funds must be returned to NCI controlled reservewithin 15 business days.
2.LBR Direct labor cannot use project contingency unless approved by NCI FME CORand CO.
3.NCI Reserves the right to request additional information
工作说明书附录:一般要求 2022 财年设施任务命令 B – 翻新和基础设施项目重点关注弗雷德里克校区 NCI 内的设施改进1 一般要求根据 FFRDC SOW,维护计划应与当前机构间协议的要素(包括任何修订)兼容。此外,在德特里克堡的美国陆军驻地 (USAG) 和弗雷德里克的 NCI 之间,承包商履行指定的职责承包商的工作和责任应包括提供指定工作所需的所有规划、规划、工程、维护、行政和管理。应按照 FFRDC SOW,附件 1,法规/认证/认可/指南进行。 2. 设施运营和计划工作管理承包商应与政府密切合作,以确定需求和计划。承包商应在项目概念、设计和收尾期间与 EHS 进行协调,以确保项目进度表中提交的项目里程碑反映 FME 和 EHS 要求 a) 计划工作管理 承包商应有权管理所有项目。工作订单的各个方面,包括但不限于使用批准的项目预算、进度和项目质量,承包商应使用定性和定量指标估算项目应急需求,必须根据任务订单条款获得批准。以及任何之前的条件承包商应向客户和 FME COR 通报项目进展情况。在任务订单执行期间,如果发现对范围、成本、进度或绩效有影响,承包商应通知。如果关键路径发生变化,通知应包括导致变化的累积事件的解释、Fragnet 和风险缓解策略,包括进度恢复和/或加速。全体董事确保每个项目b) 计划的工作收尾承包商应与 FME COR 合作制定项目收尾标准实践。
2019年9月26日
2
所有承包商业务总监流程的范围/成本/进度表的收尾考虑。
3.设施战略规划
作为母公司 IDIQ 要求的设施运营手册的开发、持续发展和完善的一部分,承包商应不断评估和分析设施、维护和工程活动的各个方面。承包商应设法考虑提高效率的程序。设施、维护、工程和改造/改造/维护/翻新/改进项目 承包商应寻求在各个方面进行改进,以提高合同履行的有效性或效率。客户反馈和利益相关者的意见。
4.质量保证/质量控制(QA/QC)
承包商应制定和维护质量保证 (QA) 和质量控制 (QC) 基线计划,记录性能和质量标准以及管理控制和评估技术,以确保组件、服务和产品符合 HHS/NIH/NCI 的设计标准承包商应确定提高所有项目领域绩效和效率的政策和程序。 承包商应建立和维护有效的质量控制 (QC) 体系,其中包括必要的计划、程序和组织。生产出一种产品符合合同要求。
承包商应提供施工质量管理 (CQM) 计划,以确保工作按照计划和规范按时在规定的预算内进行,并且承包商应为所有项目提供详细的质量控制计划 (QCP)。 > 50,000.00 美元,承包商应为所有 > 100 万美元的项目指定经过认证的质量控制经理。 承包商对遵守计划和规范负有主要责任。
5.成本控制(估算
承包商应使用历史数据、市场分析和“RS Means”软件来制定任何变更请求的成本估算和/或影响分析报告。承包商必须遵守 DRM(第 1.6.3 节)中规定的要求。还应遵循美国专业估算师协会 (ASPE) 方法。
6.会议
承包商和 NCI 指定代表之间举行以下会议,根据任务订单授予的不可分割项目应包含在适用的内容和讨论中:
1)FME运营会议(每周)
该会议包括 FME、MOSB 和 FME COR,应每周举行一次,以审查和讨论计划运营优先事项和绩效。
2)本周计划(POW)会议(每周)
2019年9月26日
3
该会议应每周举行一次,成员包括 FME、EHS、项目代表、MOSB、OSO 以及 FME 和 EHS COR,以审查所有新工单、开发中的工单和已批准工单的状态。
7.指标的跟踪和监控
根据 NCI FFRDC 操作任务指令的要求,承包商和 FME COR 应确定具有指定目标的关键绩效指标,一旦确定,承包商应跟踪和监控在不可分割任务下授予的计划工作的指标。订单时,承包商应至少跟踪和监控以下指标:
•从最初批准的时间表重新安排的工单(WO) 的百分比。
•按类型划分的工单支出:
o一般工单
o检查
o紧急情况
o纠正性维护
•计划中的WO相对于所有其他WO的百分比
•积压(资金门槛)
o特别协助
•工单积压,包括每个商店总共 30 天以上的积压工作订单
•每个商店的工单完成响应时间
•车间对 FME 计划工单、工时和总百分比的支持
8.意外事件
应急通知应包括:
1-应急使用需要的叙述性解释
2-应急日志跟踪应急使用的每个实例、金额、小计和剩余余额
3-列联指数计算
• 意外事件指数= 实际完成百分比/意外事件支出百分比。
4-适用的支持文件,包括但不限于:
•PCO
•RFI
•公告
•提交材料
•更改订单代码:
oAE 错误遗漏
o不可预见的现场条件
o用户引导的变更请求
•检查
•日程变更-Fragnet
2019年9月26日
4
额外的应急要求:
1.如果 LBR 的“最佳和最终”分包商奖励低于 LBR 分包商估算的 NCI 奖励金额,则所有超额资金必须在 15 个工作日内退还至 NCI 控制储备。
2.LBR 直接人工不得使用项目应急费用,除非得到 NCI FME COR 和 CO 批准。
3.NCI 保留要求提供更多信息的权利
项目成果
期刊论文数量(0)
专著数量(0)
科研奖励数量(0)
会议论文数量(0)
专利数量(0)
数据更新时间:{{ journalArticles.updateTime }}
{{
item.title }}
{{ item.translation_title }}
- DOI:
{{ item.doi }} - 发表时间:
{{ item.publish_year }} - 期刊:
- 影响因子:{{ item.factor }}
- 作者:
{{ item.authors }} - 通讯作者:
{{ item.author }}
数据更新时间:{{ journalArticles.updateTime }}
{{ item.title }}
- 作者:
{{ item.author }}
数据更新时间:{{ monograph.updateTime }}
{{ item.title }}
- 作者:
{{ item.author }}
数据更新时间:{{ sciAawards.updateTime }}
{{ item.title }}
- 作者:
{{ item.author }}
数据更新时间:{{ conferencePapers.updateTime }}
{{ item.title }}
- 作者:
{{ item.author }}
数据更新时间:{{ patent.updateTime }}
ETHAN DMITROVSKY其他文献
ETHAN DMITROVSKY的其他文献
{{
item.title }}
{{ item.translation_title }}
- DOI:
{{ item.doi }} - 发表时间:
{{ item.publish_year }} - 期刊:
- 影响因子:{{ item.factor }}
- 作者:
{{ item.authors }} - 通讯作者:
{{ item.author }}
{{ truncateString('ETHAN DMITROVSKY', 18)}}的其他基金
CONSOLIDATED FACILITIES REQUIREMENTS FOR FY22 TASK ORDER-A.
2022 财年任务订单 A 的综合设施要求。
- 批准号:
10716600 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别:
THIS CPFF TO IS FOR REFURBISHMENT AND INFRASTRUCTURE PROJECTS FOCUSED ON FACILITY IMPROVEMENTS WITHIN THE NCI AT FREDERICK CAMPUSMOD001
本 CPFF 用于翻新和基础设施项目,重点是弗雷德里克 CAMPUSMOD001 NCI 内的设施改进
- 批准号:
10717434 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别:
THIS CPFF TO IS FOR REFURBISHMENT AND INFRASTRUCTURE PROJECTS FOCUSED ON FACILITY IMPROVEMENTS WITHIN THE NCI AT FREDERICK CAMPUSMOD001
本 CPFF 用于翻新和基础设施项目,重点是弗雷德里克 CAMPUSMOD001 NCI 内的设施改进
- 批准号:
10788206 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别:
THIS IS A CPFF TO TO REFURBISH APA BUILDINGS (1033).
这是 CPFF 的目的,旨在翻新 APA 建筑物 (1033)。
- 批准号:
10717450 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别:
FY22 Facilities Task Order B – Refurbishment and Infrastructure Projects focused on Facility Improvements within the NCI at Frederick Campus
2022 财年设施任务订单 B — 翻新和基础设施项目,重点关注弗雷德里克校区 NCI 内的设施改进
- 批准号:
10815678 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别:
THIS IS A CPFF TO TO REFURBISH APA BUILDINGS 1034
这是 CPFF 的目的,旨在翻新 APA 大楼 1034
- 批准号:
10717424 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别:
THIS COST PLUS FIXED FEE TASK ORDER IS FOR COORDINATED FACILITIES REQUIREMENTS FOR FY22 FACILITIES BAS UPGRADE
此成本加固定费用任务订单适用于 2022 财年设施 BAS 升级的协调设施要求
- 批准号:
10717452 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别:
相似国自然基金
基于RRAM的可重构PUF电路设计与轻量级认证协议研究
- 批准号:62371226
- 批准年份:2023
- 资助金额:49 万元
- 项目类别:面上项目
5G/6G网络中无人机辅助的终端接入认证与切换认证协议研究
- 批准号:
- 批准年份:2021
- 资助金额:30 万元
- 项目类别:青年科学基金项目
抗泄漏轻量化的认证密钥交换协议
- 批准号:
- 批准年份:2020
- 资助金额:24 万元
- 项目类别:青年科学基金项目
基于蜜字的抗泄露身份认证协议研究
- 批准号:
- 批准年份:2020
- 资助金额:57 万元
- 项目类别:面上项目
边缘计算环境下设备接入认证与密钥协商协议研究
- 批准号:61902049
- 批准年份:2019
- 资助金额:25.0 万元
- 项目类别:青年科学基金项目
相似海外基金
Establishing Automated Cryopreservation System for Biospecimen Storage
建立生物标本储存自动化冷冻保存系统
- 批准号:
10533660 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别:
High-speed, portable reflectance confocal microscope (pRCM) for imaging skin cancer
用于皮肤癌成像的高速便携式反射共焦显微镜 (pRCM)
- 批准号:
10381884 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别:
Expedited Expansion Cohort Clinical Trial for Relapsed/Refractory 'no-option' Non-Hodgkin's Lymphoma/Leukemia Patients
针对复发/难治性“无选择”非霍奇金淋巴瘤/白血病患者的快速扩展队列临床试验
- 批准号:
10642955 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别:
THIS CPFF TO IS FOR REFURBISHMENT AND INFRASTRUCTURE PROJECTS FOCUSED ON FACILITY IMPROVEMENTS WITHIN THE NCI AT FREDERICK CAMPUSMOD001
本 CPFF 用于翻新和基础设施项目,重点是弗雷德里克 CAMPUSMOD001 NCI 内的设施改进
- 批准号:
10717434 - 财政年份:2022
- 资助金额:
$ 612.82万 - 项目类别: